June Progress
continued
June Progress
May Progress
continued
May Progress
April Progress
continued
April Progress
March Progress
continued
March Progress
February Progress
continued
February Progress
January Progress
continued
January Progress
December Progress
continued
December Progress
November Progress
continued
November Progress
October Progress
October Progress
continued
September Progress
September Progress
Continued
August 2020
Tower crane installation on August 24 & 25
August 2020
Undergrounding Verizon lines along Wash Blvd
August 2020
Infrastructure conduit for electrical refeed for 12th Rd N residences. DEV is expected to switchover power late Fall 2020.
July Progress
80% of excavation was completed by end of July
July Progress
cont.
June Progress
May Progress
May Progress
cont.
Pre-construction
2/24/20